Expansion
of existing underground electrical infrastructure on Arroyo Boulevard is
scheduled to begin on July 6 and end on August 26, 2011
(extended). Project
boundaries are between Seco Street and Rosemont Avenue,
on the southeast side of the Rose Bowl.
(See map here.)
The
construction work will require traffic interruptions due to partial and
temporary road closures on Seco Street and on Rosemont Avenue at Arroyo
Boulevard. Every effort will be made to minimize traffic impacts on
vehicles, bicycles, pedestrians, etc. Work will usually be done Mondays
through Fridays during daytime hours.
This is part
of a multi-phased Pasadena Water and Power Department project in the Rose
Bowl area. For more information, call (626)
744-4175.
Project
Updates
Aug.17 - The project has been extended
one week and will now end August 26.
Project
Facts
About 12,000 feet of underground electric
conduit will be installed in about 2,300 feet of trench.
Construction period is from July 6, 2011
through August 26, 2011
(extended). Weather and other circumstances
may shift the work schedule.
Construction will generally take place Monday
through Friday, from 7:00 a.m. until 3:30 p.m. to minimize
traffic impacts on vehicles, bicycles, pedestrians, etc.
Traffic interruptions in Seco Street and
Rosemont Avenue at Arroyo Boulevard will be necessary.(See
map here.)
Construction method for the installation of conduit will be
by “open cut” or trenching
Funding for the project is provided by the
city's Power Fund.